Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

BSR APPLICATIONS LIMITED

Customer named in the TEC register

9projects in the register
3.5 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Hill House Farm Solar and StorageNorton GSPStorage with solar or wind99.930 Oct 2035Not statedScoping
Cold NortonSouth Anglia Connection Node C 400kV SubstationStorage with solar or wind1,25031 Oct 2036Gate 1Scoping
Stretchford Farm Solar and StorageAbham 132kV SubstationStorage with solar or wind10030 Oct 2037Not statedScoping
Barry Road StorageSevern Connection Node A 132kV SubstationStorage11031 Oct 2037Gate 1Scoping
Stockhills FarmSevern Connection Node A 400kv SubstationStorage with solar or wind80031 Oct 2037Gate 1Scoping
Wick Moor DroveWest Country Connection Node D 400kV SubstationStorage with solar or wind50031 Oct 2037Not statedScoping
Crawcroft Lane Solar and StorageSouth Humber Connection Node A 400kVStorage with solar or wind24030 Oct 2039Gate 1Scoping
Martindale FarmHartmoor GSPStorage with solar or wind24030 Oct 2039Gate 1Scoping
Thurcroft StorageLeeds South Connection Node B 132kV SubstationStorage20030 Oct 2039Gate 1Scoping

Recent changes

  • Stockhills FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Barry Road StorageEngland and Wales, StorageMarked as Gate 1
  • Martindale FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Thurcroft StorageEngland and Wales, StorageConnection point changed from Thurcroft GSP to Leeds South Connection Node B 132kV Substation
  • Thurcroft StorageEngland and Wales, StorageMarked as Gate 1
  • Crawcroft Lane Solar and StorageEngland and Wales, Storage with solar or windConnection point changed from New Lincolnshire Connection Substation to South Humber Connection Node A 400kV
  • Crawcroft Lane Solar and StorageEngland and Wales, Storage with solar or windMarked as Gate 1
  • Cold NortonEngland and Wales, Storage with solar or windMarked as Gate 1
  • Crawcroft Lane Solar and StorageEngland and Wales, Storage with solar or windAdded to the registerNew
  • Martindale FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Stretchford Farm Solar and StorageEngland and Wales, Storage with solar or windAdded to the registerNew
  • Thurcroft StorageEngland and Wales, StorageAdded to the registerNew
  • Barry Road StorageEngland and Wales, StorageAdded to the registerNew
  • Hill House Farm Solar and StorageEngland and Wales, Storage with solar or windAdded to the registerNew
  • Wick Moor DroveEngland and Wales, Storage with solar or windAdded to the registerNew
  • Cold NortonEngland and Wales, Storage with solar or windConnection point changed from Rayleigh 400kV Substation to South Anglia Connection Node C 400kV Substation
  • Cold NortonEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 31 Oct 2036 (+36 months)+36 mo
  • Stockhills FarmEngland and Wales, Storage with solar or windConnection point changed from Iron Acton 275kV Substation to Severn Connection Node A 400kv Substation
  • Stockhills FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Cold NortonEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO