Pentir 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Fferm Solar Pentir | LIGHTSOURCE SPV 191 LIMITED | Storage | 57 | 31 Oct 2028 +18 mo | Gate 2 | Consents Approved |
| Pentir Green Energy Centre | INNOVA RENEWABLES LIMITED | Storage with solar or wind | 1,025 | 30 Oct 2037 | Gate 1 | Awaiting Consents |
Left the register since January 2021: Codling Park Wind Farm (1 GW).
Recent changes
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- Fferm Solar PentirEngland and Wales, StorageConnection date moved from 1 May 2027 to 31 Oct 2028 (+18 months)+18 mo
- Fferm Solar PentirEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Fferm Solar PentirEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- Fferm Solar PentirEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2037)
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 31 Oct 2037)
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENTIR NO LIMITED to INNOVA RENEWABLES LIMITED
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to PENTIR NO LIMITED
- Fferm Solar PentirEngland and Wales, StorageTechnology changed from Solar to Storage, Solar
- Codling Park Wind FarmEngland and Wales, Offshore windLeft the register (1,000 MW from 1 Oct 2028)1,000 MW
- Fferm Solar PentirEngland and Wales, StorageConnection point changed from Pentir GSP to Pentir 400kV Substation
- Codling Park Wind FarmEngland and Wales, Offshore windConnection point changed from Pentir GSP to Pentir 400kV Substation
- Fferm Solar PentirEngland and Wales, StorageConnection date moved from 1 May 2024 to 1 May 2027 (+36 months)+36 mo
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- Fferm Solar PentirEngland and Wales, StorageSubstation name updated in the register (from Pentir to Pentir GSP)
- Codling Park Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pentir to Pentir GSP)
- Fferm Solar PentirEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
- Fferm Solar PentirEngland and Wales, StorageAdded to the registerNew
- Codling Park Wind FarmEngland and Wales, Offshore windConnection date moved from 31 Oct 2024 to 1 Oct 2028 (+47 months)+47 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?