Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Pentir 400kV Substation

England and Wales, National Grid Electricity Transmission

2projects in the register
1.1 GWstill to connect
57 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Fferm Solar PentirLIGHTSOURCE SPV 191 LIMITEDStorage5731 Oct 2028 +18 moGate 2Consents Approved
Pentir Green Energy CentreINNOVA RENEWABLES LIMITEDStorage with solar or wind1,02530 Oct 2037Gate 1Awaiting Consents

Left the register since January 2021: Codling Park Wind Farm (1 GW).

Recent changes

  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
  • Fferm Solar PentirEngland and Wales, StorageConnection date moved from 1 May 2027 to 31 Oct 2028 (+18 months)+18 mo
  • Fferm Solar PentirEngland and Wales, StorageStatus changed from Scoping to Consents Approved
  • Fferm Solar PentirEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
  • Fferm Solar PentirEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2037)
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 31 Oct 2037)
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENTIR NO LIMITED to INNOVA RENEWABLES LIMITED
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to PENTIR NO LIMITED
  • Fferm Solar PentirEngland and Wales, StorageTechnology changed from Solar to Storage, Solar
  • Codling Park Wind FarmEngland and Wales, Offshore windLeft the register (1,000 MW from 1 Oct 2028)1,000 MW
  • Fferm Solar PentirEngland and Wales, StorageConnection point changed from Pentir GSP to Pentir 400kV Substation
  • Codling Park Wind FarmEngland and Wales, Offshore windConnection point changed from Pentir GSP to Pentir 400kV Substation
  • Fferm Solar PentirEngland and Wales, StorageConnection date moved from 1 May 2024 to 1 May 2027 (+36 months)+36 mo
  • Pentir Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
  • Fferm Solar PentirEngland and Wales, StorageSubstation name updated in the register (from Pentir to Pentir GSP)
  • Codling Park Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pentir to Pentir GSP)
  • Fferm Solar PentirEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
  • Fferm Solar PentirEngland and Wales, StorageAdded to the registerNew
  • Codling Park Wind FarmEngland and Wales, Offshore windConnection date moved from 31 Oct 2024 to 1 Oct 2028 (+47 months)+47 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO