QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Transmission / Projects / England and Wales

Codling Park Wind Farm

CODLING WIND PARK III LIMITED at Pentir 400kV Substation

Connection date
Left 31 May 2024
Gate
Not stated
Status
Scoping
Technology
Offshore wind
Total capacity
1,000 MW
Connected now
0 MW
Still to connect
1,000 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Directly Connected
Region
England and Wales
Project number
PRO-000098
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 31 May 2024 register
    Left the register (1,000 MW from 1 Oct 2028)
  • 28 Jul 2023 register
    Connection point changed from Pentir GSP to Pentir 400kV Substation
  • 23 Dec 2022 register
    Substation name updated in the register (from Pentir to Pentir GSP)
  • 30 Apr 2021 register
    Connection date moved from 31 Oct 2024 to 1 Oct 2028 (+47 months)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO