INNOVA RENEWABLES LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Pentir Green Energy Centre | Pentir 400kV Substation | Storage with solar or wind | 1,025 | 30 Oct 2037 | Gate 1 | Awaiting Consents |
| Patmores (Mott Street) | London North East Connection Node A 132kv Substation | Storage | 200 | 31 Oct 2038 | Gate 1 | Scoping |
Left the register since January 2021: Kearsley North Green Energy Centre (400 MW), Swansea North Green Energy Centre (400 MW).
Recent changes
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- Patmores (Mott Street)England and Wales, StorageConnection point changed from Brimsdown GSP (EPN) to London North East Connection Node A 132kv Substation
- Patmores (Mott Street)England and Wales, StorageMarked as Gate 1
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windMarked as Gate 1
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2037)
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 31 Oct 2037)
- Patmores (Mott Street)England and Wales, StorageAdded to the registerNew
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from PENTIR NO LIMITED to INNOVA RENEWABLES LIMITED
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to PENTIR NO LIMITED
- Pentir Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- Kearsley North Green Energy CentreEngland and Wales, Storage with solar or windLeft the register (400 MW from 31 Oct 2028)400 MW
- Swansea North Green Energy CentreEngland and Wales, Storage with solar or windLeft the register (400 MW from 30 Oct 2028)400 MW
- Kearsley North Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- Swansea North Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose