Fferm Solar Pentir
- Connection date
- 31 Oct 2028 +18 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 9 Sep 2024
Gwynedd, reference C24/0532/25/LL · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001049
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 14 Jul 2026 registerConnection date moved from 1 May 2027 to 31 Oct 2028 (+18 months)
- 14 Jul 2026 registerStatus changed from Scoping to Consents Approved
- 14 Jul 2026 registerTechnology changed from Storage, Solar to Storage
- 14 Jul 2026 registerGiven a Gate 2 connection offer
- 28 Feb 2025 registerTechnology changed from Solar to Storage, Solar
- 28 Jul 2023 registerConnection point changed from Pentir GSP to Pentir 400kV Substation
- 30 Jun 2023 registerConnection date moved from 1 May 2024 to 1 May 2027 (+36 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Pentir to Pentir GSP)
- 25 Feb 2022 registerCapacity changed from 50 MW to 57 MW
- 31 Dec 2021 registerAdded to the register
Also at Pentir 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total.