Walsoken Battery
Walsoken Limited at North Anglia Connection Node D 132kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 25 Jul 2025
King's Lynn and West Norfolk, reference 23/02302/FM · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002690
- In the register since
- November 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerConnection date moved from 30 Oct 2033 to 31 Oct 2034 (+12 months)
- 27 Aug 2024 registerConnection point changed from Walpole 132kV Substation to North Anglia Connection Node D 132kV Substation
- 28 Nov 2023 registerAdded to the register
Also at North Anglia Connection Node D 132kV Substation
Substation view1 other project, 478 MW still to connect at this substation in total.