Noventum -Long Stratton
Noventum Power Solar 8 Limited at North Anglia Connection Node A 400kV
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 460 MW
- Connected now
- 0 MW
- Still to connect
- 460 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004405
- In the register since
- August 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 30 Oct 2038 to 31 Oct 2034 (−48 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2038 (+48 months)
- 1 May 2026 registerMarked as Gate 1
- 27 Aug 2024 registerAdded to the register
Also at North Anglia Connection Node A 400kV
Substation view6 other projects, 3.8 GW still to connect at this substation in total. 250 MW is due to connect here before this project’s connection date of 31 Oct 2034.
- Norwich Main BESSTASWAY ENERGY PARK LIMITED, Storage with solar or wind, Gate 1Oct 2032950 MW
- Elmya Gissing BESS & PVRPC ELMYA CARNATION GISSING LIMITED, Storage with solar or wind, Gate 1Oct 2034900 MW
- GF Norwich BESSGF Norwich Energy Ltd, Storage, Gate 1Oct 2034400 MW
- Long Stratton 400ENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Oct 2034400 MW
- Long Stratton BESSField Long Stratton Ltd, Storage, Gate 1Oct 2034400 MW
- SwainsthorpeLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2037300 MW