Minety 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Minety | HB411MIN Limited | Storage | 47.5 | 31 Oct 2024 Past date | Not stated | Consents Approved |
| Fairholme BESS | HB411MIN Limited | Storage | 47.5 | 28 Feb 2025 Past date | Not stated | Consents Approved |
| Pond Hill Farm 1 | PD688IRO LTD | Storage | 47.5 | 30 Apr 2025 Past date | Not stated | Consents Approved |
| Pond Hill Farm 2 BESS | PD688IRO LTD | Storage | 47.5 | 31 May 2025 Past date | Not stated | Consents Approved |
| Somerford | PD688IRO LTD | Storage with solar or wind | 47.5 | 30 Jun 2025 Past date | Not stated | Consents Approved |
| Southfields | PD688IRO LTD | Storage with solar or wind | 47.5 | 30 Jun 2025 Past date | Not stated | Awaiting Consents |
| Dog Trap Lane | HB411MIN Limited | Storage | 47.5 | 31 Oct 2028 | Not stated | Consents Approved |
| Southfields Farm | PD688IRO LTD | Storage | 47.5 | 31 Oct 2028 | Not stated | Consents Approved |
| JBM Solar -Minety | JBM SOLAR PROJECTS 14 LTD | Storage with solar or wind | 47.5 | 30 Nov 2028 | Not stated | Scoping |
Recent changes
- Southfields FarmEngland and Wales, StorageCustomer changed from PD300RON Ltd to PD688IRO LTD
- Southfields FarmEngland and Wales, StorageCustomer changed from PD688IRO LTD to PD300RON Ltd
- JBM Solar -MinetyEngland and Wales, Storage with solar or windConnection date moved from 30 Nov 2024 to 30 Nov 2028 (+48 months)+48 mo
- JBM Solar -MinetyEngland and Wales, Storage with solar or windRenamed from Minety Tertiary (2)
- JBM Solar -MinetyEngland and Wales, Storage with solar or windConnection point changed from Minety GSP to Minety 400kV Substation
- JBM Solar -MinetyEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2024 to 30 Nov 2024 (+1 month)+1 mo
- JBM Solar -MinetyEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- SouthfieldsEngland and Wales, Storage with solar or windCustomer changed from PD503HAN LTD to PD688IRO LTD
- Dog Trap LaneEngland and Wales, StorageCustomer changed from HD381GRE Limited to HB411MIN Limited
- Dog Trap LaneEngland and Wales, StorageConnection date moved from 31 Mar 2025 to 31 Oct 2028 (+43 months)+43 mo
- SomerfordEngland and Wales, Storage with solar or windCustomer changed from PD813ETY LTD to PD688IRO LTD
- Southfields FarmEngland and Wales, StorageCustomer changed from PD300RON Ltd to PD688IRO LTD
- Southfields FarmEngland and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- Dog Trap LaneEngland and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- Pond Hill Farm 1England and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- Pond Hill Farm 2 BESSEngland and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- SomerfordEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Consents Approved
- Fairholme BESSEngland and Wales, StorageCustomer changed from HB222BRI LTD to HB411MIN Limited
- MinetyEngland and Wales, StorageRenamed from Minety Tertiary Connection
- JBM Solar -MinetyEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 47.5 MW
- Fairholme BESSEngland and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- MinetyEngland and Wales, StorageConnection point changed from Minety GSP to Minety 400kV Substation
- MinetyEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- MinetyEngland and Wales, StorageTechnology changed from Gas engines to Storage
- Southfields FarmEngland and Wales, StorageStatus changed from Scoping to Awaiting Consents
- Southfields FarmEngland and Wales, StorageAdded to the registerNew
- Pond Hill Farm 2 BESSEngland and Wales, StorageConnection date moved from 30 May 2025 to 31 May 2025 (1 day later)
- Dog Trap LaneEngland and Wales, StorageConnection point changed from Minety to Minety 400kV Substation
- Fairholme BESSEngland and Wales, StorageConnection point changed from Minety to Minety 400kV Substation
- JBM Solar -MinetyEngland and Wales, Storage with solar or windConnection point changed from Minety to Minety GSP
- MinetyEngland and Wales, StorageConnection point changed from Minety to Minety GSP
- Pond Hill Farm 1England and Wales, StorageConnection point changed from Minety to Minety 400kV Substation
- Pond Hill Farm 2 BESSEngland and Wales, StorageConnection point changed from Minety to Minety 400kV Substation
- SomerfordEngland and Wales, Storage with solar or windConnection point changed from Minety to Minety 400kV Substation
- SouthfieldsEngland and Wales, Storage with solar or windConnection point changed from Minety to Minety 400kV Substation
- Fairholme BESSEngland and Wales, StorageConnection date moved from 28 Mar 2025 to 28 Feb 2025 (−1 month)−1 mo
- MinetyEngland and Wales, StorageCapacity changed from 49.9 MW to 47.5 MW
- MinetyEngland and Wales, StorageConnection date moved from 1 Sep 2023 to 31 Oct 2024 (+14 months)+14 mo
- Dog Trap LaneEngland and Wales, StorageAdded to the registerNew
- Fairholme BESSEngland and Wales, StorageAdded to the registerNew
- Pond Hill Farm 1England and Wales, StorageAdded to the registerNew
- Pond Hill Farm 2 BESSEngland and Wales, StorageAdded to the registerNew
- SomerfordEngland and Wales, Storage with solar or windAdded to the registerNew
- SouthfieldsEngland and Wales, Storage with solar or windAdded to the registerNew
- MinetyEngland and Wales, StorageConnection date moved from 9 Jan 2023 to 1 Sep 2023 (+8 months)+8 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?