Melksham 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Melksham (Tertiary) | MELKSHAM CALNE GREEN LIMITED | Storage with solar or wind | 57 | 26 Jun 2026 Past date | Not stated | Scoping |
| JBM Solar 13 - Melksham | JBM SOLAR PROJECTS 13 LIMITED | Storage with solar or wind | 49.9 | 17 Jul 2026 Past date | Not stated | Scoping |
| Melksham | LIME DOWN SOLAR PARK LIMITED | Storage with solar or wind | 500 | 31 Jul 2030 | Not stated | Awaiting Consents |
| South Brook | JBM Solar Limited | Storage with solar or wind | 35.5 | 28 Jun 2037 | Not stated | Awaiting Consents |
| Melksham BESS & PV | ELEMENTS GREEN LIMITED | Storage with solar or wind | 800 | 15 Oct 2037 | Not stated | Scoping |
| Melkshem (Cartridge Farm) | Queequeg Renewables Ltd | Storage | 480 | 31 Oct 2037 | Not stated | Awaiting Consents |
Left the register since January 2021: Melksham Grid Park ESS & PV (90 MW), Melksham 1 Tertiary (49.9 MW), Melksham 2 Tertiary (49.9 MW), Middel Energy Park (100 MW).
Recent changes
- Melksham Grid Park ESS & PVEngland and Wales, Storage with solar or windLeft the register (90 MW from 31 Oct 2037)90 MW
- MelkshamEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
- Melksham (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2025 to 26 Jun 2026 (+8 months)+8 mo
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windTechnology changed from Thermal to Storage, Solar
- MelkshamEngland and Wales, Storage with solar or windConnection date moved from 31 Jul 2029 to 31 Jul 2030 (+12 months)+12 mo
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windConnection date moved from 14 Nov 2025 to 17 Jul 2026 (+8 months)+8 mo
- South BrookEngland and Wales, Storage with solar or windCustomer changed from DALIA HOLDINGS LTD to JBM SOLAR LIMITED
- Melksham (Tertiary)England and Wales, Storage with solar or windRestructured from 2 stages (49.9 MW from 30 Oct 2022, 7.1 MW from 31 Oct 2023) to 1 stage (57 MW from 31 Oct 2025). First connection date +36 months+36 mo
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2026 to 14 Nov 2025 (−8 months)−8 mo
- MelkshamEngland and Wales, Storage with solar or windCustomer changed from IGP SOLAR 15 LIMITED to LIME DOWN SOLAR PARK LIMITED
- Melksham Grid Park ESS & PVEngland and Wales, Storage with solar or windAdded to the registerNew
- Middel Energy ParkEngland and Wales, Storage with solar or windLeft the register (100 MW from 30 Sep 2029)100 MW
- Melkshem (Cartridge Farm)England and Wales, StorageAdded to the registerNew
- Melksham BESS & PVEngland and Wales, Storage with solar or windAdded to the registerNew
- South BrookEngland and Wales, Storage with solar or windCustomer changed from JBM SOLAR PROJECTS (UK) LTD to DALIA HOLDINGS LTD
- Middel Energy ParkEngland and Wales, Storage with solar or windAdded to the registerNew
- South BrookEngland and Wales, Storage with solar or windAdded to the registerNew
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windSubstation name updated in the register (from Melksham 400kV to Melksham 400kV Substation)
- MelkshamEngland and Wales, Storage with solar or windSubstation name updated in the register (from Melksham 400kV to Melksham 400kV Substation)
- Melksham (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Melksham 400kV to Melksham 400kV Substation)
- Melksham (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2022 to 30 Oct 2022 (1 day earlier)
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2024 to 30 Jun 2026 (+20 months)+20 mo
- JBM Solar 13 - MelkshamEngland and Wales, Storage with solar or windAdded to the registerNew
- MelkshamEngland and Wales, Storage with solar or windAdded to the registerNew
- Melksham 1 TertiaryEngland and Wales, StorageLeft the register (49.9 MW from 30 Apr 2024)49.9 MW
- Melksham 2 TertiaryEngland and Wales, StorageLeft the register (49.9 MW from 30 Apr 2024)49.9 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose