JBM Solar 13 - Melksham
- Connection date
- 17 Jul 2026
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000495
- In the register since
- August 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerTechnology changed from Thermal to Storage, Solar
- 27 Jun 2025 registerCapacity changed from 50 MW to 49.9 MW
- 27 Jun 2025 registerConnection date moved from 14 Nov 2025 to 17 Jul 2026 (+8 months)
- 29 Oct 2024 registerConnection date moved from 30 Jun 2026 to 14 Nov 2025 (−8 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Melksham 400kV to Melksham 400kV Substation)
- 30 Jun 2022 registerConnection date moved from 30 Oct 2024 to 30 Jun 2026 (+20 months)
- 31 Aug 2021 registerAdded to the register
Also at Melksham 400kV Substation
Substation view5 other projects, 1.9 GW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 17 Jul 2026.
- Melksham (Tertiary)MELKSHAM CALNE GREEN LIMITED, Storage with solar or wind, Not statedJun 202657 MW
- MelkshamLIME DOWN SOLAR PARK LIMITED, Storage with solar or wind, Not statedJul 2030500 MW
- South BrookJBM Solar Limited, Storage with solar or wind, Not statedJun 203735.5 MW
- Melksham BESS & PVELEMENTS GREEN LIMITED, Storage with solar or wind, Not statedOct 2037800 MW
- Melkshem (Cartridge Farm)Queequeg Renewables Ltd, Storage, Not statedOct 2037480 MW