Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Lister Drive 275kV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
114 MWstill to connect
57 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Lister Drive ShawCarnegie (BES) LtdStorage571 Sep 2026 Past dateNot statedScoping
Lister Battery (formerly Lister Drive)LISTER BATTERY LTDStorage5730 Sep 2029 +71 moGate 2Consents Approved
Lister Drive 275kVLISTER DRIVE SOLUTIONS LIMITEDOther0ConnectedNot statedBuilt

Left the register since January 2021: Lister Drive (49.9 MW), Lister Drive (57 MW).

Recent changes

  • Lister Battery (formerly Lister Drive)England and Wales, StorageStatus changed from Scoping to Consents Approved
  • Lister Battery (formerly Lister Drive)England and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Lister Battery (formerly Lister Drive)England and Wales, StorageConnection date moved from 31 Oct 2023 to 30 Sep 2029 (+71 months)+71 mo
  • Lister Drive ShawEngland and Wales, StorageConnection date moved from 1 May 2025 to 1 Sep 2026 (+16 months)+16 mo
  • Lister Drive ShawEngland and Wales, StorageConnection point changed from Carnegie Road Substation to Lister Drive 275kV Substation
  • Lister Drive ShawEngland and Wales, StorageConnection point changed from Lister Drive 275kV to Carnegie Road Substation
  • Lister Drive 275kVEngland and Wales, OtherConnection date removed (was 23 Jun 2022)
  • Lister Drive 275kVEngland and Wales, OtherStatus changed from Under Construction/Commissioning to Built
  • Lister Drive ShawEngland and Wales, StorageConnection date moved from 30 Jun 2023 to 1 May 2025 (+22 months)+22 mo
  • Lister Battery (formerly Lister Drive)England and Wales, StorageSubstation name updated in the register (from Lister Drive 275kV to Lister Drive 275kV Substation)
  • Lister Drive ShawEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
  • Lister Drive ShawEngland and Wales, StorageCustomer changed from Carnegie BES Limited to SHAW-ENERGI LTD
  • Lister Drive ShawEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
  • Lister Drive 275kVEngland and Wales, OtherSubstation name updated in the register (from Lister Drive 275KV to Lister Drive 275KV Substation)
  • Lister Drive 275kVEngland and Wales, OtherConnection date moved from 17 Dec 2021 to 23 Jun 2022 (+6 months)+6 mo
  • Lister Battery (formerly Lister Drive)England and Wales, StorageCapacity changed from 49.9 MW to 57 MW
  • Lister Battery (formerly Lister Drive)England and Wales, StorageConnection date moved from 31 Oct 2021 to 31 Oct 2023 (+24 months)+24 mo
  • Lister Drive 275kVEngland and Wales, OtherAdded to the registerNew
  • Lister Drive ShawEngland and Wales, StorageAdded to the registerNew
  • Lister DriveEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
  • Lister DriveEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
  • Lister DriveEngland and Wales, StorageConnection date moved from 1 May 2023 to 30 Jun 2023 (+2 months)+2 mo
  • Lister Battery (formerly Lister Drive)England and Wales, StorageAdded to the registerNew
  • Lister DriveEngland and Wales, StorageLeft the register (49.9 MW from 31 Oct 2021)49.9 MW
  • Lister DriveEngland and Wales, StorageConnection date moved from 5 Jan 2023 to 1 May 2023 (+4 months)+4 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO