Lister Drive 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Lister Drive Shaw | Carnegie (BES) Ltd | Storage | 57 | 1 Sep 2026 Past date | Not stated | Scoping |
| Lister Battery (formerly Lister Drive) | LISTER BATTERY LTD | Storage | 57 | 30 Sep 2029 +71 mo | Gate 2 | Consents Approved |
| Lister Drive 275kV | LISTER DRIVE SOLUTIONS LIMITED | Other | 0 | Connected | Not stated | Built |
Left the register since January 2021: Lister Drive (49.9 MW), Lister Drive (57 MW).
Recent changes
- Lister Battery (formerly Lister Drive)England and Wales, StorageStatus changed from Scoping to Consents Approved
- Lister Battery (formerly Lister Drive)England and Wales, StorageGiven a Gate 2 connection offerGate 2
- Lister Battery (formerly Lister Drive)England and Wales, StorageConnection date moved from 31 Oct 2023 to 30 Sep 2029 (+71 months)+71 mo
- Lister Drive ShawEngland and Wales, StorageConnection date moved from 1 May 2025 to 1 Sep 2026 (+16 months)+16 mo
- Lister Drive ShawEngland and Wales, StorageConnection point changed from Carnegie Road Substation to Lister Drive 275kV Substation
- Lister Drive ShawEngland and Wales, StorageConnection point changed from Lister Drive 275kV to Carnegie Road Substation
- Lister Drive 275kVEngland and Wales, OtherConnection date removed (was 23 Jun 2022)
- Lister Drive 275kVEngland and Wales, OtherStatus changed from Under Construction/Commissioning to Built
- Lister Drive ShawEngland and Wales, StorageConnection date moved from 30 Jun 2023 to 1 May 2025 (+22 months)+22 mo
- Lister Battery (formerly Lister Drive)England and Wales, StorageSubstation name updated in the register (from Lister Drive 275kV to Lister Drive 275kV Substation)
- Lister Drive ShawEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
- Lister Drive ShawEngland and Wales, StorageCustomer changed from Carnegie BES Limited to SHAW-ENERGI LTD
- Lister Drive ShawEngland and Wales, StorageCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
- Lister Drive 275kVEngland and Wales, OtherSubstation name updated in the register (from Lister Drive 275KV to Lister Drive 275KV Substation)
- Lister Drive 275kVEngland and Wales, OtherConnection date moved from 17 Dec 2021 to 23 Jun 2022 (+6 months)+6 mo
- Lister Battery (formerly Lister Drive)England and Wales, StorageCapacity changed from 49.9 MW to 57 MW
- Lister Battery (formerly Lister Drive)England and Wales, StorageConnection date moved from 31 Oct 2021 to 31 Oct 2023 (+24 months)+24 mo
- Lister Drive 275kVEngland and Wales, OtherAdded to the registerNew
- Lister Drive ShawEngland and Wales, StorageAdded to the registerNew
- Lister DriveEngland and Wales, StorageLeft the register (57 MW from 30 Jun 2023)57 MW
- Lister DriveEngland and Wales, StorageCapacity changed from 50 MW to 57 MW
- Lister DriveEngland and Wales, StorageConnection date moved from 1 May 2023 to 30 Jun 2023 (+2 months)+2 mo
- Lister Battery (formerly Lister Drive)England and Wales, StorageAdded to the registerNew
- Lister DriveEngland and Wales, StorageLeft the register (49.9 MW from 31 Oct 2021)49.9 MW
- Lister DriveEngland and Wales, StorageConnection date moved from 5 Jan 2023 to 1 May 2023 (+4 months)+4 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?