Lister Drive Shaw
- Connection date
- 1 Sep 2026
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001342
- In the register since
- September 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerConnection date moved from 1 May 2025 to 1 Sep 2026 (+16 months)
- 27 Sep 2024 registerConnection point changed from Carnegie Road Substation to Lister Drive 275kV Substation
- 30 Jun 2023 registerConnection point changed from Lister Drive 275kV to Carnegie Road Substation
- 31 Mar 2023 registerConnection date moved from 30 Jun 2023 to 1 May 2025 (+22 months)
- 31 Jan 2023 registerCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
- 23 Dec 2022 registerCustomer changed from Carnegie BES Limited to SHAW-ENERGI LTD
- 29 Nov 2022 registerCustomer changed from SHAW-ENERGI LTD to Carnegie BES Limited
- 28 Sep 2021 registerAdded to the register
Also at Lister Drive 275kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total.