Lister Battery (formerly Lister Drive)
- Connection date
- 30 Sep 2029 +71 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001088
- In the register since
- April 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 21 Sep 2026 registerGiven a Gate 2 connection offer
- 17 Jul 2026 registerConnection date moved from 31 Oct 2023 to 30 Sep 2029 (+71 months)
- 28 Feb 2023 registerSubstation name updated in the register (from Lister Drive 275kV to Lister Drive 275kV Substation)
- 30 Nov 2021 registerCapacity changed from 49.9 MW to 57 MW
- 30 Nov 2021 registerConnection date moved from 31 Oct 2021 to 31 Oct 2023 (+24 months)
- 30 Apr 2021 registerAdded to the register
Also at Lister Drive 275kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 30 Sep 2029.