Lister Drive 275kV
LISTER DRIVE SOLUTIONS LIMITED at Lister Drive 275kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Reactive compensation
- Total capacity
- 0 MW
- Connected now
- 0 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001248
- In the register since
- November 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Mar 2023 registerConnection date removed (was 23 Jun 2022)
- 31 Mar 2023 registerStatus changed from Under Construction/Commissioning to Built
- 29 Jul 2022 registerSubstation name updated in the register (from Lister Drive 275KV to Lister Drive 275KV Substation)
- 30 Jun 2022 registerConnection date moved from 17 Dec 2021 to 23 Jun 2022 (+6 months)
- 30 Nov 2021 registerAdded to the register
Also at Lister Drive 275kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total.