Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Lairg GSP

North Scotland, SSEN Transmission

3projects in the register
135 MWstill to connect
84.8 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Lairg II Wind FarmLAIRG II LLPOnshore wind5016 Jul 2027 +9 moGate 2Consents Approved
Strath TirryStrath Tirry Wind Energy 2021 LtdOnshore wind34.819 Dec 2029Gate 2Awaiting Consents
NAVAS BESSOPDE UK LIMITEDStorage49.931 Oct 2033Gate 1Scoping

Recent changes

  • Strath TirryNorth Scotland, Onshore windStatus changed from Scoping to Awaiting Consents
  • Strath TirryNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
  • Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Lairg II 132kV Substation to Lairg GSP
  • Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Dalchork 132kV Substation to Lairg II 132kV Substation
  • Lairg II Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Oct 2026 to 16 Jul 2027 (+9 months)+9 mo
  • Lairg II Wind FarmNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
  • NAVAS BESSNorth Scotland, StorageMarked as Gate 1
  • Lairg II Wind FarmNorth Scotland, Onshore windCustomer changed from ENERGYFARM UK LAIRG LLP to LAIRG II LLP
  • Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Lairg GSP to Dalchork 132kV Substation
  • Strath TirryNorth Scotland, Onshore windRestructured from 2 stages (20 MW from 19 Dec 2029, 14.8 MW from 19 Dec 2029) to 1 stage (34.8 MW from 19 Dec 2029)
  • NAVAS BESSNorth Scotland, StorageAdded to the registerNew
  • Strath TirryNorth Scotland, Onshore windStage 1: Connection date moved from 31 Oct 2025 to 19 Dec 2029 (+50 months)+50 mo
  • Strath TirryNorth Scotland, Onshore windStage 1: Technology changed from Storage, Onshore wind to Onshore wind
  • Strath TirryNorth Scotland, Onshore windStage 2: Connection date moved from 30 Sep 2027 to 19 Dec 2029 (+27 months)+27 mo
  • Strath TirryNorth Scotland, Onshore windStage 2: Technology changed from Storage, Onshore wind to Onshore wind
  • Strath TirryNorth Scotland, Onshore windRenamed from Strath Tirry (keep)
  • Strath TirryNorth Scotland, Onshore windRenamed from Strath Tirry
  • Strath TirryNorth Scotland, Onshore windRestructured from 1 stage (34.8 MW from 20 Aug 2024) to 2 stages (20 MW from 31 Oct 2025, 14.8 MW from 30 Sep 2027). First connection date +14 months+14 mo
  • Strath TirryNorth Scotland, Onshore windCustomer changed from STRATH TIRRY WIND ENERGY LIMITED to Strath Tirry Wind Energy 2021 Ltd
  • Strath TirryNorth Scotland, Onshore windAdded to the registerNew
  • Lairg II Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)+12 mo
  • Lairg II Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Lairg to Lairg GSP)
  • Lairg II Wind FarmNorth Scotland, Onshore windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.