Lairg II Wind Farm
- Connection date
- 16 Jul 2027 +9 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 2 Nov 2021
Highland, reference 21/00849/FUL · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001434
- In the register since
- April 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 11 Aug 2026 registerConnection point changed from Lairg II 132kV Substation to Lairg GSP
- 30 Jun 2026 registerConnection point changed from Dalchork 132kV Substation to Lairg II 132kV Substation
- 30 Jun 2026 registerConnection date moved from 31 Oct 2026 to 16 Jul 2027 (+9 months)
- 30 Jun 2026 registerGiven a Gate 2 connection offer
- 27 Mar 2026 registerCustomer changed from ENERGYFARM UK LAIRG LLP to LAIRG II LLP
- 19 Dec 2025 registerConnection point changed from Lairg GSP to Dalchork 132kV Substation
- 28 Jan 2022 registerConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)
- 30 Nov 2021 registerSubstation name updated in the register (from Lairg to Lairg GSP)
- 30 Apr 2021 registerAdded to the register
Also at Lairg GSP
Substation view2 other projects, 135 MW still to connect at this substation in total.