Strath Tirry
- Connection date
- 19 Dec 2029
- Gate
- Gate 2
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 34.8 MW
- Connected now
- 0 MW
- Still to connect
- 34.8 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001363
- In the register since
- March 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 3 Nov 2026 registerStatus changed from Scoping to Awaiting Consents
- 30 Oct 2026 registerGiven a Gate 2 connection offer
- 29 Jul 2025 registerRestructured from 2 stages (20 MW from 19 Dec 2029, 14.8 MW from 19 Dec 2029) to 1 stage (34.8 MW from 19 Dec 2029)
- 27 Jun 2025 registerStage 1: Connection date moved from 31 Oct 2025 to 19 Dec 2029 (+50 months)
- 27 Jun 2025 registerStage 1: Technology changed from Storage, Onshore wind to Onshore wind
- 27 Jun 2025 registerStage 2: Connection date moved from 30 Sep 2027 to 19 Dec 2029 (+27 months)
- 27 Jun 2025 registerStage 2: Technology changed from Storage, Onshore wind to Onshore wind
- 28 Jun 2024 registerRenamed from Strath Tirry (keep)
- 29 Sep 2023 registerRenamed from Strath Tirry
- 28 Jul 2023 registerRestructured from 1 stage (34.8 MW from 20 Aug 2024) to 2 stages (20 MW from 31 Oct 2025, 14.8 MW from 30 Sep 2027). First connection date +14 months
- 29 Apr 2022 registerCustomer changed from STRATH TIRRY WIND ENERGY LIMITED to Strath Tirry Wind Energy 2021 Ltd
- 30 Mar 2022 registerAdded to the register
Also at Lairg GSP
Substation view2 other projects, 135 MW still to connect at this substation in total. 50 MW is due to connect here before this project’s connection date of 19 Dec 2029.