LAIRG II LLP
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Lairg II Wind Farm | Lairg GSP | Onshore wind | 50 | 16 Jul 2027 +9 mo | Gate 2 | Consents Approved |
Recent changes
- Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Lairg II 132kV Substation to Lairg GSP
- Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Dalchork 132kV Substation to Lairg II 132kV Substation
- Lairg II Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Oct 2026 to 16 Jul 2027 (+9 months)+9 mo
- Lairg II Wind FarmNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Lairg II Wind FarmNorth Scotland, Onshore windCustomer changed from ENERGYFARM UK LAIRG LLP to LAIRG II LLP
- Lairg II Wind FarmNorth Scotland, Onshore windConnection point changed from Lairg GSP to Dalchork 132kV Substation
- Lairg II Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)+12 mo
- Lairg II Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Lairg to Lairg GSP)
- Lairg II Wind FarmNorth Scotland, Onshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?