Lackenby 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Dogger Bank Project C | DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED | Offshore wind | 1,200 | 1 Apr 2025 Past date | Not stated | Consents Approved |
| Crathorne Estate BESS and Solar Farm | Exagen Development Limited | Storage with solar or wind | 600 | 30 Oct 2035 | Gate 1 | Scoping |
| Sofia Offshore Wind Farm | SOFIA OFFSHORE WIND FARM LIMITED | Offshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Sofia Offshore Wind FarmEngland and Wales, Offshore wind1,320 MW now connectedConnected
- Sofia Offshore Wind FarmEngland and Wales, Offshore windStatus changed from Scoping to Built
- Sofia Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Dogger Bank 220kV Offshores to Lackenby 400kV Substation
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Teeside Connection Node A 132kV Substation to Lackenby 400kV Substation
- Crathorne Estate BESS and Solar FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Lackenby GSP to Teeside Connection Node A 132kV Substation
- Sofia Offshore Wind FarmEngland and Wales, Offshore windStage removed (0 MW)
- Sofia Offshore Wind FarmEngland and Wales, Offshore windStage 1: Capacity changed from 132 MW to 0 MW
- Sofia Offshore Wind FarmEngland and Wales, Offshore windStage 1: Connection date removed (was 1 Sep 2024)
- Sofia Offshore Wind FarmEngland and Wales, Offshore windRestructured from 1 stage (1,188 MW from 1 Apr 2025) to 1 stage (1,320 MW from 30 Jan 2026). First connection date +10 months+10 mo
- Crathorne Estate BESS and Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
- Dogger Bank Project CEngland and Wales, Offshore windSubstation name updated in the register (from Lackenby to Lackenby GSP)
- Sofia Offshore Wind FarmEngland and Wales, Offshore windRestructured from 1 stage (1,320 MW from 1 Apr 2024) to 2 stages (132 MW from 1 Sep 2024, 1,188 MW from 1 Apr 2025). First connection date +5 months+5 mo
- Dogger Bank Project CEngland and Wales, Offshore windCustomer changed from DOGGERBANK OFFSHORE WIND FARM PROJECT 3 HOLDCO LIMITED to DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED
- Sofia Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2023 to 1 Apr 2024 (+12 months)+12 mo
- Dogger Bank Project CEngland and Wales, Offshore windCapacity changed from 1,320 MW to 1,200 MW
- Dogger Bank Project CEngland and Wales, Offshore windConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Dogger Bank Project CEngland and Wales, Offshore windRenamed from Dogger Bank Project 2
- Dogger Bank Project CEngland and Wales, Offshore windCapacity changed from 1,500 MW to 1,320 MW
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Dogger Bank 220kV Offshores to Lackenby
- Dogger Bank Project CEngland and Wales, Offshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
- Sofia Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?