DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Dogger Bank Project C | Lackenby 400kV Substation | Offshore wind | 1,200 | 1 Apr 2025 Past date | Not stated | Consents Approved |
Recent changes
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Teeside Connection Node A 132kV Substation to Lackenby 400kV Substation
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Lackenby GSP to Teeside Connection Node A 132kV Substation
- Dogger Bank Project CEngland and Wales, Offshore windSubstation name updated in the register (from Lackenby to Lackenby GSP)
- Dogger Bank Project CEngland and Wales, Offshore windCustomer changed from DOGGERBANK OFFSHORE WIND FARM PROJECT 3 HOLDCO LIMITED to DOGGERBANK OFFSHORE WIND FARM PROJECT 3 PROJCO LIMITED
- Dogger Bank Project CEngland and Wales, Offshore windCapacity changed from 1,320 MW to 1,200 MW
- Dogger Bank Project CEngland and Wales, Offshore windConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Dogger Bank Project CEngland and Wales, Offshore windRenamed from Dogger Bank Project 2
- Dogger Bank Project CEngland and Wales, Offshore windCapacity changed from 1,500 MW to 1,320 MW
- Dogger Bank Project CEngland and Wales, Offshore windConnection point changed from Dogger Bank 220kV Offshores to Lackenby
- Dogger Bank Project CEngland and Wales, Offshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?