Sofia Offshore Wind Farm
SOFIA OFFSHORE WIND FARM LIMITED at Lackenby 400kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Offshore wind
- Total capacity
- 1,320 MW
- Connected now
- 1,320 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000404
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Jul 2026 register1,320 MW now connected
- 7 Jul 2026 registerStatus changed from Scoping to Built
- 23 Dec 2025 registerConnection point changed from Dogger Bank 220kV Offshores to Lackenby 400kV Substation
- 29 Aug 2025 registerStage removed (0 MW)
- 29 Jul 2025 registerStage 1: Capacity changed from 132 MW to 0 MW
- 29 Jul 2025 registerStage 1: Connection date removed (was 1 Sep 2024)
- 29 Jul 2025 registerRestructured from 1 stage (1,188 MW from 1 Apr 2025) to 1 stage (1,320 MW from 30 Jan 2026). First connection date +10 months
- 30 Aug 2022 registerRestructured from 1 stage (1,320 MW from 1 Apr 2024) to 2 stages (132 MW from 1 Sep 2024, 1,188 MW from 1 Apr 2025). First connection date +5 months
- 31 May 2022 registerConnection date moved from 1 Apr 2023 to 1 Apr 2024 (+12 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)
Also at Lackenby 400kV Substation
Substation view2 other projects, 1.8 GW still to connect at this substation in total.