- Connection date
- 31 Oct 2027 +25 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 30 Apr 2024
Knowsley, reference 23/02008/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001084
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 31 Oct 2027 | Gate 2 | Consents Approved |
| 2 | 0 | 7.1 | 57 | 30 Oct 2037 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerStage 2: Gate marking removed (was Gate 2)
- 5 Oct 2026 registerStage 1: Given a Gate 2 connection offer
- 5 Oct 2026 registerStage 2: Status changed from Scoping to Consents Approved
- 5 Oct 2026 registerStage 2: Given a Gate 2 connection offer
- 1 Oct 2026 registerConnection point changed from Kirkby 275kV Substation to Kirkby 275/33kV Substation
- 24 Jul 2026 registerStage 1: Connection date moved from 30 Sep 2025 to 31 Oct 2027 (+25 months)
- 29 Aug 2025 registerCustomer changed from HD001KIR LTD to KIRKBY BATTERY STORAGE LTD
- 29 Jul 2025 registerStage 1: Technology changed from Gas engines to Storage
- 29 Jul 2025 registerStage 2: Technology changed from Gas engines to Storage
- 29 Sep 2023 registerRestructured from 1 stage (49.5 MW from 1 Oct 2023) to 2 stages (49.9 MW from 30 Sep 2025, 7.1 MW from 30 Oct 2037). First connection date +24 months
- 28 Feb 2023 registerRenamed from Coopers Lane Kirkby
- 28 Feb 2023 registerTechnology changed from Gas (CCGT) to Gas engines
- 29 Jul 2022 registerSubstation name updated in the register (from Kirkby 275kV to Kirkby 275kV Substation)
- 29 Oct 2021 registerConnection date moved from 30 Oct 2022 to 1 Oct 2023 (+11 months)
Also at Kirkby 275/33kV Substation
Substation view1 other project, 114 MW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 31 Oct 2027.