Kincardine North 400kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| EcoKincardine | Econergy International Limited | Storage with solar or wind | 249 | 31 Oct 2030 +27 mo | Gate 1 | Scoping |
| Hawkhill BESS | GPC Project 12 Ltd | Storage | 500 | 31 Oct 2031 | Gate 1 | Scoping |
| Tulliallan BESS | IGP ENERGY STORAGE 6 LIMITED | Storage | 500 | 31 Oct 2031 | Gate 1 | Scoping |
Recent changes
- EcoKincardineSouth Scotland, Storage with solar or windConnection date moved from 31 Jul 2028 to 31 Oct 2030 (+27 months)+27 mo
- EcoKincardineSouth Scotland, Storage with solar or windMarked as Gate 1
- Tulliallan BESSSouth Scotland, StorageConnection date moved from 31 Jul 2031 to 31 Oct 2031 (+3 months)+3 mo
- Tulliallan BESSSouth Scotland, StorageConnection date moved from 31 Oct 2031 to 31 Jul 2031 (−3 months)−3 mo
- Hawkhill BESSSouth Scotland, StorageMarked as Gate 1
- Tulliallan BESSSouth Scotland, StorageMarked as Gate 1
- Hawkhill BESSSouth Scotland, StorageCustomer changed from Apatura Battery Ltd to GPC Project 12 Ltd
- Hawkhill BESSSouth Scotland, StorageConnection point changed from Kincardine GSP to Kincardine North 400kV Substation
- Tulliallan BESSSouth Scotland, StorageConnection point changed from Kincardine 275kV to Kincardine North 400kV Substation
- Tulliallan BESSSouth Scotland, StorageSubstation name updated in the register (from Kincardine 275kV Substation to Kincardine 275kV)
- Hawkhill BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- Hawkhill BESSSouth Scotland, StorageAdded to the registerNew
- EcoKincardineSouth Scotland, Storage with solar or windAdded to the registerNew
- Tulliallan BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?