Tulliallan BESS
IGP ENERGY STORAGE 6 LIMITED at Kincardine North 400kV Substation
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003619
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 31 Jul 2031 to 31 Oct 2031 (+3 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2031 to 31 Jul 2031 (−3 months)
- 9 Dec 2025 registerMarked as Gate 1
- 28 Feb 2025 registerConnection point changed from Kincardine 275kV to Kincardine North 400kV Substation
- 27 Sep 2024 registerSubstation name updated in the register (from Kincardine 275kV Substation to Kincardine 275kV)
- 29 Dec 2023 registerAdded to the register
Also at Kincardine North 400kV Substation
Substation view2 other projects, 1.2 GW still to connect at this substation in total. 249 MW is due to connect here before this project’s connection date of 31 Oct 2031.