EcoKincardine
Econergy International Limited at Kincardine North 400kV Substation
- Connection date
- 31 Oct 2030 +27 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003557
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerConnection date moved from 31 Jul 2028 to 31 Oct 2030 (+27 months)
- 16 Oct 2026 registerMarked as Gate 1
- 30 Jan 2024 registerAdded to the register
Also at Kincardine North 400kV Substation
Substation view2 other projects, 1.2 GW still to connect at this substation in total.