Ouse Energy Storage
- Connection date
- 27 Oct 2027
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001861
- In the register since
- April 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Nov 2024 registerConnection date moved from 24 Aug 2026 to 27 Oct 2027 (+14 months)
- 23 Dec 2022 registerConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- 29 Apr 2022 registerAdded to the register
Also at Kemsley 400kV Substation
Substation view1 other project, 249 MW still to connect at this substation in total.