Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Highview Hunterston East Cryobattery

HVS SITECO LTD at Hunterston East 400kV

Connection date
31 Oct 2027
Gate
Not stated
Status
Consents Approved
Technology
Demand + Storage + Reactive compensation
Total capacity
200 MW
Connected now
0 MW
Still to connect
200 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001348
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Apr 2025 register
    Customer changed from HVS SITEGO LTD to HVS SITECO LTD
  • 28 Feb 2025 register
    Customer changed from HVS GRIDCO LTD to HVS SITEGO LTD
  • 26 Nov 2024 register
    Status changed from Scoping to Consents Approved
  • 27 Sep 2024 register
    Substation name updated in the register (from Hunterston East 400kV Substation to Hunterston East 400kV)
  • 27 Sep 2024 register
    Capacity changed from 99.8 MW to 200 MW
  • 27 Sep 2024 register
    Connection date moved from 30 Jun 2024 to 31 Oct 2027 (+40 months)
  • 27 Sep 2024 register
    Technology changed from Storage, Reactive compensation to Demand, Storage, Reactive compensation
  • 23 Dec 2022 register
    Connection point changed from Highview Hunterston East Cryobattery 400kV Substation to Hunterston East 400kV Substation
  • 30 Nov 2021 register
    Technology changed from Storage to Storage, Reactive compensation
  • 30 Jul 2021 register
    Connection date moved from 30 Oct 2024 to 30 Jun 2024 (−4 months)
  • 30 Apr 2021 register
    Technology changed from Storage, Reactive compensation to Storage

Also at Hunterston East 400kV

Substation view

1 other project, 400 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO