Hawthorn Pit 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Icewind Hawthorn Pit | KARI ENERGY LIMITED | Offshore wind | 1,000 | 31 Oct 2031 | Gate 1 | Scoping |
| Morven A Offshore Wind Farm (Prev Phoenix 1A) | Morven Offshore Wind Limited | Offshore wind | 1,500 | 31 Oct 2031 | Not stated | Scoping |
| Hawthorn Pit Green Energy Centre | HAWTHORN PIT NG LIMITED | Storage with solar or wind | 1,025 | 31 Oct 2032 | Not stated | Awaiting Consents |
| Isenau Eight | Isenau Energy Storage Resources Eight Limited | Storage | 249 | 31 Oct 2033 | Not stated | Scoping |
| ER HTP Energy | ER PROJECT DEVELOPMENT CO LIMITED | Storage with solar or wind | 57 | 30 Jun 2034 | Not stated | Scoping |
Recent changes
- Icewind Hawthorn PitEngland and Wales, Offshore windMarked as Gate 1
- Isenau EightEngland and Wales, StorageConnection point changed from Hawthorn Pit GSP to Hawthorn Pit 400kV Substation
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2039)
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to HAWTHORN PIT NG LIMITED
- Morven A Offshore Wind Farm (Prev Phoenix 1A)England and Wales, Offshore windConnection point changed from Phoenix 1A 275/66kV Offshore Substation to Hawthorn Pit 400kV Substation
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2039)
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from HAWThORN PIT NO LIMITED to INNOVA RENEWABLES LIMITED
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to HAWThORN PIT NO LIMITED
- Icewind Hawthorn PitEngland and Wales, Offshore windCustomer changed from Hecate Offshore Wind Limited to KARI ENERGY LIMITED
- Morven A Offshore Wind Farm (Prev Phoenix 1A)England and Wales, Offshore windCustomer changed from BP ALTERNATIVE ENERGY INVESTMENTS LIMITED to Morven Offshore Wind Limited
- Isenau EightEngland and Wales, StorageConnection date moved from 22 Jun 2023 to 31 Oct 2033 (+124 months)+124 mo
- Morven A Offshore Wind Farm (Prev Phoenix 1A)England and Wales, Offshore windRenamed from Phoenix 1A Offshore Wind Farm
- Morven A Offshore Wind Farm (Prev Phoenix 1A)England and Wales, Offshore windTransmission owner changed from SHET to NGET
- Isenau EightEngland and Wales, StorageAdded to the registerNew
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windConnection point changed from Hawthorn Pit GSP to Hawthorn Pit 400kV Substation
- Icewind Hawthorn PitEngland and Wales, Offshore windConnection point changed from Hawthorn Pit GSP to Hawthorn Pit 400kV Substation
- ER HTP EnergyEngland and Wales, Storage with solar or windAdded to the registerNew
- Hawthorn Pit Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- Icewind Hawthorn PitEngland and Wales, Offshore windCustomer changed from HECATE INDEPENDENT POWER LIMITED to Hecate Offshore Wind Limited
- Icewind Hawthorn PitEngland and Wales, Offshore windSubstation name updated in the register (from Hawthorn Pit to Hawthorn Pit GSP)
- Icewind Hawthorn PitEngland and Wales, Offshore windAdded to the registerNew
- Morven A Offshore Wind Farm (Prev Phoenix 1A)England and Wales, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?