Harker 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Harker Green Energy Centre | Blackdyke BESS Limited | Storage with solar or wind | 400 | 30 Oct 2028 | Not stated | Awaiting Consents |
| BESS Harker | REWE 4 LIMITED | Storage | 200 | 30 May 2031 | Not stated | Consents Approved |
| Harker PV & BESS Sub | HARKER ENERGY PARK LIMITED | Storage with solar or wind | 250 | 1 Nov 2037 | Gate 1 | Scoping |
| Low Harker BESS | Energi Generation 14 Ltd | Storage with solar or wind | 400 | 30 Nov 2037 | Not stated | Scoping |
| NEL Story | STORY ENERGY LIMITED | Storage | 240 | 30 Nov 2037 | Gate 1 | Scoping |
| ESB Harker BESS | ESB (HARKER) LTD | Storage | 342 | 31 Oct 2039 | Not stated | Scoping |
Recent changes
- Harker Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 2 stages (400 MW from 30 Oct 2028, 625 MW from 30 Oct 2032) to 1 stage (400 MW from 30 Oct 2028)
- Harker PV & BESS SubEngland and Wales, Storage with solar or windMarked as Gate 1
- NEL StoryEngland and Wales, StorageMarked as Gate 1
- NEL StoryEngland and Wales, StorageCustomer changed from STORY FUTURE ENERGY LIMITED to STORY ENERGY LIMITED
- Harker Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2036)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2037)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from HARKER GREEN NG LIMITED to Blackdyke BESS Limited
- Harker Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Status changed from Scoping to Awaiting Consents
- Harker Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Storage, Solar, Onshore wind
- Harker Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Storage, Solar, Onshore wind
- Harker Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2036)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
- ESB Harker BESSEngland and Wales, StorageAdded to the registerNew
- Harker Green Energy CentreEngland and Wales, Storage with solar or windNew stage added (625 MW from 30 Oct 2032)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (400 MW from 30 Oct 2028) to 1 stage (400 MW from 30 Oct 2028)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to MARKER GREEN NG LIMITED
- BESS HarkerEngland and Wales, StorageCustomer changed from CSWE 4 LIMITED to REWE 4 LIMITED
- BESS HarkerEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Harker PV & BESS SubEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 50) Limited to HARKER ENERGY PARK LIMITED
- NEL StoryEngland and Wales, StorageCustomer changed from Willow Energy Limited to STORY FUTURE ENERGY LIMITED
- Harker PV & BESS SubEngland and Wales, Storage with solar or windAdded to the registerNew
- NEL StoryEngland and Wales, StorageAdded to the registerNew
- Low Harker BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- BESS HarkerEngland and Wales, StorageAdded to the registerNew
- Harker Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Harker 400kV to Harker 400kV Substation)
- Harker Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose