Projects / England and Wales
- Connection date
- 30 May 2031
- Gate
- Not stated
- Status
- Consented
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002010
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Harker 400kV Substation
Substation view5 other projects, 2.5 GW still to connect at this substation in total.
- Harker Green Energy CentreBlackdyke BESS Limited, Storage with solar or wind, Not statedOct 20281 GW
- Harker PV & BESS SubHARKER ENERGY PARK LIMITED, Storage with solar or wind, Gate 1Nov 2037250 MW
- Low Harker BESSEnergi Generation 14 Ltd, Storage with solar or wind, Not statedNov 2037400 MW
- NEL StorySTORY ENERGY LIMITED, Storage, Gate 1Nov 2037240 MW
- ESB Harker BESSESB (HARKER) LTD, Storage, Not statedOct 2039342 MW