Low Harker BESS
- Connection date
- 30 Nov 2037
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 18 Jul 2024
Cumberland, reference 24/0093 · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003873
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jun 2023 registerAdded to the register
Also at Harker 400kV Substation
Substation view5 other projects, 1.8 GW still to connect at this substation in total. 850 MW is due to connect here before this project’s connection date of 30 Nov 2037.
- Harker Green Energy CentreBlackdyke BESS Limited, Storage with solar or wind, Not statedOct 2028400 MW
- BESS HarkerREWE 4 LIMITED, Storage, Not statedMay 2031200 MW
- Harker PV & BESS SubHARKER ENERGY PARK LIMITED, Storage with solar or wind, Gate 1Nov 2037250 MW
- NEL StorySTORY ENERGY LIMITED, Storage, Gate 1Nov 2037240 MW
- ESB Harker BESSESB (HARKER) LTD, Storage, Not statedOct 2039342 MW