Harker PV & BESS Sub
- Connection date
- 1 Nov 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002615
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 25 Aug 2026 registerMarked as Gate 1
- 28 Jun 2024 registerCustomer changed from O&G Solar (SPV 50) Limited to HARKER ENERGY PARK LIMITED
- 29 Sep 2023 registerAdded to the register
Also at Harker 400kV Substation
Substation view5 other projects, 1.8 GW still to connect at this substation in total. 600 MW is due to connect here before this project’s connection date of 1 Nov 2037.
- Harker Green Energy CentreBlackdyke BESS Limited, Storage with solar or wind, Not statedOct 2028400 MW
- BESS HarkerREWE 4 LIMITED, Storage, Not statedMay 2031200 MW
- Low Harker BESSEnergi Generation 14 Ltd, Storage with solar or wind, Not statedNov 2037400 MW
- NEL StorySTORY ENERGY LIMITED, Storage, Gate 1Nov 2037240 MW
- ESB Harker BESSESB (HARKER) LTD, Storage, Not statedOct 2039342 MW