Derbyshire Connection Node A 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Daventry High Impact Green Energy Hub (HIGEH) 1 | TELIS ENERGY UK LIMITED | Multi-technology hub | 1,000 | 30 Oct 2037 +48 mo | Gate 1 | Scoping |
| Park Farm Hybrid Solar and BESS | VOLTALIA UK LTD | Storage with solar or wind | 332 | 30 Oct 2037 | Not stated | Scoping |
| West Haddon | West Haddon 10 Renewables Limited | Solar | 1,000 | 30 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Daventry High Impact Green Energy Hub (HIGEH) 1England and Wales, Multi-technology hubConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- Daventry High Impact Green Energy Hub (HIGEH) 1England and Wales, Multi-technology hubMarked as Gate 1
- West HaddonEngland and Wales, SolarMarked as Gate 1
- Daventry High Impact Green Energy Hub (HIGEH) 1England and Wales, Multi-technology hubConnection point changed from New Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windConnection point changed from Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- West HaddonEngland and Wales, SolarConnection date moved from 31 Oct 2039 to 30 Oct 2037 (−24 months)−24 mo
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windConnection point changed from Derbyshire Connection Node A 400kV Substation to Patford Bridge 400kV Substation
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windConnection point changed from Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2035 to 31 Oct 2037 (+24 months)+24 mo
- West HaddonEngland and Wales, SolarConnection point changed from West Haddon 400kV to Derbyshire Connection Node A 400kV Substation
- West HaddonEngland and Wales, SolarCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to West Haddon 10 Renewables Limited
- Park Farm Hybrid Solar and BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- Daventry High Impact Green Energy Hub (HIGEH) 1England and Wales, Multi-technology hubAdded to the registerNew
- West HaddonEngland and Wales, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?