Projects / Company
VOLTALIA UK LTD
Customer named in the TEC register
8projects in the register
1.5 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bowsheil Solar and Battery | Bowsheils 132kV Substation | Storage with solar or wind | 167 | 31 Oct 2031 | Not stated | Awaiting consent |
| Springfield Solar and Battery | Branxton 400/132kV | Storage with solar or wind | 167 | 31 Oct 2031 | Not stated | Scoping |
| Peat Law Renewable Energy Park | Peat Law Renewable Energy Park 132kV Substation | Storage with solar or wind | 253 | 30 May 2033 | Gate 1 | Scoping |
| Whiteminhill Renewable Energy Park | Whiteminhill 275/33kV Substation | Storage with solar or wind | 220 | 31 Oct 2036 | Not stated | Scoping |
| Craigdarroch Hybrid Wind and BESS | Craigdarroch Hybrid Wind & BESS 132kV Substation | Storage with solar or wind | 159 | 30 Jun 2037 | Gate 1 | Scoping |
| Park Farm Hybrid Solar and BESS | Derbyshire Connection Node A 400kV Substation | Storage with solar or wind | 332 | 30 Oct 2037 | Not stated | Scoping |
| Larks Green Farm BESS | Iron Acton 132kV Substation | Storage | 100 | 31 Oct 2037 | Gate 1 | Scoping |
| Quintfall Forest Hybrid Wind and BESS 1 | Gills Bay 132kV | Storage with solar or wind | 98.5 | 31 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Bowsheil Solar and BatterySouth Scotland, Storage with solar or windStatus changed from Scoping to Awaiting consent
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose