Daventry High Impact Green Energy Hub (HIGEH) 1
TELIS ENERGY UK LIMITED at Derbyshire Connection Node A 400kV Substation
- Connection date
- 30 Oct 2037 +48 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Nuclear + Solar + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003686
- In the register since
- November 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)
- 10 Oct 2026 registerMarked as Gate 1
- 21 Apr 2026 registerConnection point changed from New Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- 28 Nov 2023 registerAdded to the register
Also at Derbyshire Connection Node A 400kV Substation
Substation view2 other projects, 2.3 GW still to connect at this substation in total.