Park Farm Hybrid Solar and BESS
VOLTALIA UK LTD at Derbyshire Connection Node A 400kV Substation
- Connection date
- 30 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 332 MW
- Connected now
- 0 MW
- Still to connect
- 332 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003850
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Mar 2026 registerConnection point changed from Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- 24 Dec 2024 registerConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- 26 Nov 2024 registerConnection point changed from Derbyshire Connection Node A 400kV Substation to Patford Bridge 400kV Substation
- 29 Oct 2024 registerConnection point changed from Patford Bridge 400kV Substation to Derbyshire Connection Node A 400kV Substation
- 29 Oct 2024 registerConnection date moved from 31 Oct 2035 to 31 Oct 2037 (+24 months)
- 30 Jan 2024 registerAdded to the register
Also at Derbyshire Connection Node A 400kV Substation
Substation view2 other projects, 2.3 GW still to connect at this substation in total.