Daines 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Daines BESS | SSE DAINES BESS LIMITED | Storage | 600 | 27 Oct 2028 | Not stated | Scoping |
| Daines Green Energy Centre | DAINES GREEN NG LIMITED | Storage with solar or wind | 480 | 31 Oct 2030 | Not stated | Scoping |
| Carrington Lane BESS | Apatura Battery Ltd | Storage | 1,800 | 30 Oct 2037 | Gate 1 | Scoping |
| Daines BESS | DAINES ENERGY PARK LIMITED | Storage | 250 | 30 Nov 2037 | Gate 1 | Scoping |
Recent changes
- Carrington Lane BESSEngland and Wales, StorageMarked as Gate 1
- Daines BESSEngland and Wales, StorageMarked as Gate 1
- Daines BESSEngland and Wales, StorageStage removed (0 MW from 1 Nov 2037)
- Daines Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2032)
- Daines Green Energy CentreEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2033)
- Daines Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to DAINES GREEN NG LIMITED
- Daines BESSEngland and Wales, StorageNew stage added (0 MW from 1 Nov 2037)
- Daines Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (480 MW from 30 Oct 2028) to 3 stages (480 MW from 31 Oct 2030, 0 MW from 31 Oct 2032, 0 MW from 31 Oct 2033). First connection date +24 months+24 mo
- Daines Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from DAINES GREEN NG LIMITED to INNOVA RENEWABLES LIMITED
- Daines Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to DAINES GREEN NG LIMITED
- Carrington Lane BESSEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- Daines BESSEngland and Wales, StorageCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE DAINES BESS LTD
- Carrington Lane BESSEngland and Wales, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- Daines BESSEngland and Wales, StorageCustomer changed from O&G Solar (SPV 48) Limited to DAINES ENERGY PARK LIMITED
- Daines BESSEngland and Wales, StorageRestructured from 1 stage (600 MW from 27 Oct 2028) to 1 stage (600 MW from 27 Oct 2028)
- Daines BESSEngland and Wales, StorageRestructured from 1 stage (600 MW from 1 Nov 2029) to 1 stage (600 MW from 27 Oct 2028). First connection date −12 months−12 mo
- Carrington Lane BESSEngland and Wales, StorageAdded to the registerNew
- Daines BESSEngland and Wales, StorageAdded to the registerNew
- Daines BESSEngland and Wales, StorageSubstation name updated in the register (from Daines 400kV to Daines 400kV Substation)
- Daines BESSEngland and Wales, StorageAdded to the registerNew
- Daines Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose