Daines Green Energy Centre
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage + Solar
- Total capacity
- 480 MW
- Connected now
- 0 MW
- Still to connect
- 480 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001902
- In the register since
- May 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerStage removed (0 MW from 31 Oct 2032)
- 30 Sep 2025 registerStage removed (0 MW from 31 Oct 2033)
- 29 Aug 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to DAINES GREEN NG LIMITED
- 27 Jun 2025 registerRestructured from 1 stage (480 MW from 30 Oct 2028) to 3 stages (480 MW from 31 Oct 2030, 0 MW from 31 Oct 2032, 0 MW from 31 Oct 2033). First connection date +24 months
- 29 Apr 2025 registerCustomer changed from DAINES GREEN NG LIMITED to INNOVA RENEWABLES LIMITED
- 28 Mar 2025 registerCustomer changed from INNOVA RENEWABLES LIMITED to DAINES GREEN NG LIMITED
- 31 May 2022 registerAdded to the register
Also at Daines 400kV Substation
Substation view3 other projects, 3.1 GW still to connect at this substation in total. 600 MW is due to connect here before this project’s connection date of 31 Oct 2030.