Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Apatura Battery Ltd

Customer named in the TEC register

13projects in the register
4.4 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Highland BESSHighland BESS 132kV SubstationStorage12030 May 2030Gate 1Scoping
Andrew BESSAndrew BESS 132kV SubstationStorage10031 Jul 2030Gate 1Scoping
Murroch BESSStrathleven GSPStorage20022 May 2031Not statedScoping
Whitecraig BESSDalkeith 400kV SubstationStorage20030 Jun 2031Gate 1Scoping
Bridge BESSTorness 400/132kVStorage15031 Oct 2031Not statedScoping
Kirklands Farm BESSWestfield 132/33kVStorage20031 Oct 2031Gate 1Scoping
Leslie 200MW BESSLeslie 200MW BESS 275kV SubstationStorage20031 May 2032Gate 1Scoping
Bendsmoor BESSBendsmoor BESS 400Kv SubstationStorage50030 Jun 2032Gate 1Scoping
Kirkcaldy BESSKirkcaldy BESS 132kV SubstationStorage10031 Oct 2032Gate 1Scoping
Farm 100MW BESSThurso South 275kV SubstationStorage10031 Oct 2033Gate 1Scoping
Tewitt Farm BESSLeeds North Connection Node D 400kV SubstationStorage20030 Oct 2035Gate 1Scoping
Carrington Lane BESSDaines 400kV SubstationStorage1,80030 Oct 2037Gate 1Scoping
Partridge Farm BESSSellindge 400kV SubstationStorage50031 Oct 2037Gate 1Scoping

Recent changes

  • Carrington Lane BESSEngland and Wales, StorageMarked as Gate 1
  • Farm 100MW BESSNorth Scotland, StorageMarked as Gate 1
  • Leslie 200MW BESSSouth Scotland, StorageMarked as Gate 1
  • Bendsmoor BESSSouth Scotland, StorageMarked as Gate 1
  • Tewitt Farm BESSEngland and Wales, StorageMarked as Gate 1
  • Andrew BESSSouth Scotland, StorageAdded to the registerNew
  • Partridge Farm BESSEngland and Wales, StorageMarked as Gate 1
  • Kirklands Farm BESSSouth Scotland, StorageMarked as Gate 1
  • Highland BESSNorth Scotland, StorageMarked as Gate 1
  • Kirkcaldy BESSSouth Scotland, StorageMarked as Gate 1
  • Whitecraig BESSSouth Scotland, StorageMarked as Gate 1
  • Murroch BESSSouth Scotland, StorageConnection point changed from Murroch BESS 132kV Substation to Strathleven GSP
  • Leslie 200MW BESSSouth Scotland, StorageAdded to the registerNew
  • Bridge BESSSouth Scotland, StorageConnection point changed from Brdige BESS 400/132Kv Substation to Torness 400/132kV
  • Bendsmoor BESSSouth Scotland, StorageConnection point changed from Gretna 400/132kV to Bendsmoor BESS 400Kv Substation
  • Bridge BESSSouth Scotland, StorageConnection point changed from Torness 400/132kV to Brdige BESS 400/132Kv Substation
  • Highland BESSNorth Scotland, StorageConnection point changed from Boat of Garten GSP to Highland BESS 132kV Substation
  • Kirkcaldy BESSSouth Scotland, StorageConnection point changed from Glenniston GSP to Kirkcaldy BESS 132kV Substation
  • Murroch BESSSouth Scotland, StorageConnection point changed from Strathleven GSP to Murroch BESS 132kV Substation
  • Tewitt Farm BESSEngland and Wales, StorageConnection point changed from Bradford West GSP to Leeds North Connection Node D 400kV Substation
  • Carrington Lane BESSEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
  • Partridge Farm BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 31 Oct 2037 (+48 months)+48 mo
  • Tewitt Farm BESSEngland and Wales, StorageConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
  • Kirklands Farm BESSSouth Scotland, StorageSubstation name updated in the register (from Westfield GSP to Westfield 132/33kV)
  • Tewitt Farm BESSEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 31 Oct 2035 (−24 months)−24 mo
  • Bendsmoor BESSSouth Scotland, StorageConnection point changed from Gretna 400kV Substation to Gretna 400/132kV
  • Bridge BESSSouth Scotland, StorageSubstation name updated in the register (from Torness GSP to Torness 400/132kV)
  • Bendsmoor BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Bridge BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Carrington Lane BESSEngland and Wales, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Farm 100MW BESSNorth Scotland, StorageAdded to the registerNew
  • Highland BESSNorth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Kirkcaldy BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Kirklands Farm BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Murroch BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Partridge Farm BESSEngland and Wales, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Tewitt Farm BESSEngland and Wales, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Whitecraig BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
  • Kirkcaldy BESSSouth Scotland, StorageAdded to the registerNew
  • Whitecraig BESSSouth Scotland, StorageAdded to the registerNew
  • Carrington Lane BESSEngland and Wales, StorageAdded to the registerNew
  • Highland BESSNorth Scotland, StorageAdded to the registerNew
  • Bridge BESSSouth Scotland, StorageAdded to the registerNew
  • Partridge Farm BESSEngland and Wales, StorageAdded to the registerNew
  • Tewitt Farm BESSEngland and Wales, StorageAdded to the registerNew
  • Bendsmoor BESSSouth Scotland, StorageAdded to the registerNew
  • Murroch BESSSouth Scotland, StorageAdded to the registerNew
  • Kirklands Farm BESSSouth Scotland, StorageAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO