Daines BESS
- Connection date
- 27 Oct 2028
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 15 May 2025
Trafford, reference 115160/FUL/24 · Source: REPD - Technology
- Storage
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002050
- In the register since
- September 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerStage removed (0 MW from 1 Nov 2037)
- 29 Jul 2025 registerNew stage added (0 MW from 1 Nov 2037)
- 24 Dec 2024 registerCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE DAINES BESS LTD
- 31 May 2024 registerRestructured from 1 stage (600 MW from 27 Oct 2028) to 1 stage (600 MW from 27 Oct 2028)
- 26 Apr 2024 registerRestructured from 1 stage (600 MW from 1 Nov 2029) to 1 stage (600 MW from 27 Oct 2028). First connection date −12 months
- 23 Dec 2022 registerSubstation name updated in the register (from Daines 400kV to Daines 400kV Substation)
- 30 Sep 2022 registerAdded to the register
Also at Daines 400kV Substation
Substation view3 other projects, 3.1 GW still to connect at this substation in total.