Narachan Wind Farm
- Connection date
- 30 Apr 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 72.6 MW
- Connected now
- 0 MW
- Still to connect
- 72.6 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001926
- In the register since
- August 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Feb 2025 registerConnection date moved from 30 Nov 2028 to 30 Apr 2030 (+17 months)
- 31 Oct 2023 registerConnection date moved from 30 Apr 2027 to 30 Nov 2028 (+19 months)
- 29 Aug 2023 registerAdded to the register
Also at Carradale 1 GSP
Substation view3 other projects, 72.6 MW still to connect at this substation in total.