Bramley 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bramley (tertiary) | BRAMLEY SOLAR LIMITED | Storage with solar or wind | 57 | 30 Oct 2027 +14 mo | Gate 2 | Under Construction/Commissioning |
| Bramley BESS | BRAMLEY BESS LIMITED | Storage | 57 | 30 Oct 2027 +25 mo | Gate 2 | Under Construction/Commissioning |
| Burghfield | SSE GENERATION LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Bramley BESSEngland and Wales, StorageStage 2: Gate marking removed (was Gate 2)
- Bramley (tertiary)England and Wales, Storage with solar or windStatus changed from Scoping to Under Construction/Commissioning
- Bramley BESSEngland and Wales, StorageStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- Bramley BESSEngland and Wales, StorageStage 2: Status changed from Consents Approved to Under Construction/Commissioning
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 16 Aug 2026 to 30 Oct 2027 (+14 months)+14 mo
- Bramley BESSEngland and Wales, StorageStage 1: Connection date moved from 29 Sep 2025 to 30 Oct 2027 (+25 months)+25 mo
- Bramley BESSEngland and Wales, StorageStage 1: Given a Gate 2 connection offerGate 2
- Bramley BESSEngland and Wales, StorageStage 2: Given a Gate 2 connection offerGate 2
- Bramley (tertiary)England and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 15 Aug 2026 to 16 Aug 2026 (1 day later)
- Bramley (tertiary)England and Wales, Storage with solar or windConnection point changed from Bramley to Bramley 400kV Substation
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2023 to 15 Aug 2026 (+33 months)+33 mo
- Bramley (tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to BRAMLEY SOLAR LIMITED
- Bramley (tertiary)England and Wales, Storage with solar or windConnection point changed from Bramley 400kV Substation to Bramley
- Bramley BESSEngland and Wales, StorageRestructured from 1 stage (50 MW from 1 Jul 2024) to 2 stages (50 MW from 29 Sep 2025, 7 MW from 31 Oct 2037). First connection date +15 months+15 mo
- Bramley BESSEngland and Wales, StorageRenamed from Bramley Solar Farm
- Bramley BESSEngland and Wales, StorageRenamed from Bramley BESS
- Bramley BESSEngland and Wales, StorageTechnology changed from Storage to Solar
- Bramley BESSEngland and Wales, StorageRenamed from Bramley Solar Farm
- Bramley BESSEngland and Wales, StorageTechnology changed from Solar to Storage
- Bramley BESSEngland and Wales, StorageCustomer changed from AGR SOLAR 5 LIMITED to BRAMLEY BESS LIMITED
- Bramley (tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Bramley 400kV to Bramley 400kV Substation)
- Bramley BESSEngland and Wales, StorageSubstation name updated in the register (from Bramley 400kV to Bramley 400kV Substation)
- BurghfieldEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Bramley to Bramley 400kV Substation
- Bramley BESSEngland and Wales, StorageConnection date moved from 1 Jul 2023 to 1 Jul 2024 (+12 months)+12 mo
- Bramley BESSEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose