BRAMLEY SOLAR LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bramley (tertiary) | Bramley 400kV Substation | Storage with solar or wind | 57 | 30 Oct 2027 +14 mo | Gate 2 | Under Construction/Commissioning |
Recent changes
- Bramley (tertiary)England and Wales, Storage with solar or windStatus changed from Scoping to Under Construction/Commissioning
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 16 Aug 2026 to 30 Oct 2027 (+14 months)+14 mo
- Bramley (tertiary)England and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 15 Aug 2026 to 16 Aug 2026 (1 day later)
- Bramley (tertiary)England and Wales, Storage with solar or windConnection point changed from Bramley to Bramley 400kV Substation
- Bramley (tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2023 to 15 Aug 2026 (+33 months)+33 mo
- Bramley (tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to BRAMLEY SOLAR LIMITED
- Bramley (tertiary)England and Wales, Storage with solar or windConnection point changed from Bramley 400kV Substation to Bramley
- Bramley (tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Bramley 400kV to Bramley 400kV Substation)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?