Bramley (tertiary)
- Connection date
- 30 Oct 2027 +14 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000396
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 7 Aug 2026 registerConnection date moved from 16 Aug 2026 to 30 Oct 2027 (+14 months)
- 7 Jul 2026 registerGiven a Gate 2 connection offer
- 30 Sep 2025 registerConnection date moved from 15 Aug 2026 to 16 Aug 2026 (1 day later)
- 31 Jan 2025 registerConnection point changed from Bramley to Bramley 400kV Substation
- 29 Oct 2024 registerConnection date moved from 31 Oct 2023 to 15 Aug 2026 (+33 months)
- 26 Mar 2024 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to BRAMLEY SOLAR LIMITED
- 26 Mar 2024 registerConnection point changed from Bramley 400kV Substation to Bramley
- 30 Mar 2022 registerSubstation name updated in the register (from Bramley 400kV to Bramley 400kV Substation)
Also at Bramley 400kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total.