Bramley BESS
- Connection date
- 30 Oct 2027 +25 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001104
- In the register since
- March 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 50 | 50 | 30 Oct 2027 | Gate 2 | Under Construction/Commissioning |
| 2 | 0 | 7 | 57 | 31 Oct 2037 | Not stated | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerStage 2: Gate marking removed (was Gate 2)
- 18 Sep 2026 registerStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- 18 Sep 2026 registerStage 2: Status changed from Consents Approved to Under Construction/Commissioning
- 7 Aug 2026 registerStage 1: Connection date moved from 29 Sep 2025 to 30 Oct 2027 (+25 months)
- 7 Aug 2026 registerStage 1: Given a Gate 2 connection offer
- 7 Aug 2026 registerStage 2: Given a Gate 2 connection offer
- 28 Jul 2023 registerRestructured from 1 stage (50 MW from 1 Jul 2024) to 2 stages (50 MW from 29 Sep 2025, 7 MW from 31 Oct 2037). First connection date +15 months
- 31 Jan 2023 registerRenamed from Bramley Solar Farm
- 23 Dec 2022 registerRenamed from Bramley BESS
- 23 Dec 2022 registerTechnology changed from Storage to Solar
- 29 Nov 2022 registerRenamed from Bramley Solar Farm
- 29 Nov 2022 registerTechnology changed from Solar to Storage
- 31 May 2022 registerCustomer changed from AGR SOLAR 5 LIMITED to BRAMLEY BESS LIMITED
- 30 Mar 2022 registerSubstation name updated in the register (from Bramley 400kV to Bramley 400kV Substation)
- 25 Feb 2022 registerConnection date moved from 1 Jul 2023 to 1 Jul 2024 (+12 months)
- 30 Mar 2021 registerAdded to the register
Also at Bramley 400kV Substation
Substation view2 other projects, 114 MW still to connect at this substation in total.