Bicker Fen 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bicker Fen 2 Solar | AGR SOLAR 3 LIMITED | Storage with solar or wind | 57 | 27 Jul 2026 Past date | Not stated | Awaiting Consents |
| Bicker Fen 1 Solar | AGR SOLAR 2 LIMITED | Storage with solar or wind | 57.1 | 31 Oct 2026 Past date +13 mo | Gate 2 | Under Construction/Commissioning |
| Heckington Fen Solar Park | Ecotricity (Heck Fen Solar) Limited | Storage with solar or wind | 400 | 1 Oct 2028 | Not stated | Scoping |
| Bicker Fenn Energy Park | BEACON FEN ENERGY PARK LIMITED | Storage with solar or wind | 600 | 1 Jun 2029 | Not stated | Scoping |
Recent changes
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Consents Approved
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Status changed from Awaiting Consents to Consents Approved
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Gate marking removed (was Gate 2)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Capacity changed from 50 MW to 50 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 26 Sep 2025 to 31 Oct 2026 (+13 months)+13 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Given a Gate 2 connection offerGate 2
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Capacity changed from 7 MW to 7.1 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Connection date moved from 1 Apr 2035 to 1 Apr 2033 (−24 months)−24 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
- Heckington Fen Solar ParkEngland and Wales, Storage with solar or windCustomer changed from ECOTRICITY GENERATION LIMITED to Ecotricity (Heck Fen Solar) Limited
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windStage removed (0 MW from 1 Jun 2033)
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windStage removed (0 MW from 30 Oct 2033)
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windNew stage added (0 MW from 1 Jun 2033)
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2033)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 May 2025 to 26 Sep 2025 (+4 months)+4 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Technology changed from Solar to Storage, Solar
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Technology changed from Solar to Storage, Solar
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Sep 2025 to 27 Jul 2026 (+10 months)+10 mo
- Heckington Fen Solar ParkEngland and Wales, Storage with solar or windConnection date moved from 1 Oct 2027 to 1 Oct 2028 (+12 months)+12 mo
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windStage removed (600 MW from 1 Jun 2024)
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windRenamed from Bicker Fen
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windNew stage added (600 MW from 1 Jun 2024)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Sep 2025 to 30 May 2025 (−4 months)−4 mo
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windCustomer changed from PEPPERHILL SOLAR FARM LIMITED to BEACON FEN ENERGY PARK LIMITED
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windRestructured from 1 stage (50 MW from 31 Oct 2023) to 2 stages (50 MW from 30 Sep 2025, 7 MW from 1 Apr 2035). First connection date +23 months+23 mo
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windRestructured from 1 stage (50 MW from 1 Jul 2024) to 2 stages (50 MW from 30 Sep 2025, 7 MW from 1 Apr 2033). First connection date +15 months+15 mo
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windCustomer changed from BICKER FEN ENERGY PARK LIMITED to PEPPERHILL SOLAR FARM LIMITED
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windCustomer changed from LOW CARBON SOLAR PARK 16 LIMITED to BICKER FEN ENERGY PARK LIMITED
- Heckington Fen Solar ParkEngland and Wales, Storage with solar or windAdded to the registerNew
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection point changed from Bicker Fen GSP to Bicker Fen 400kV Substation
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windConnection point changed from Bicker Fen GSP to Bicker Fen 400kV Substation
- Bicker Fenn Energy ParkEngland and Wales, Storage with solar or windAdded to the registerNew
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windSubstation name updated in the register (from Bicker Fen to Bicker Fen GSP)
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windSubstation name updated in the register (from Bicker Fen to Bicker Fen GSP)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection date moved from 1 Jul 2023 to 31 Oct 2023 (+4 months)+4 mo
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windConnection date moved from 1 Nov 2023 to 1 Jul 2024 (+8 months)+8 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection date moved from 7 Jan 2023 to 1 Jul 2023 (+6 months)+6 mo
- Bicker Fen 2 SolarEngland and Wales, Storage with solar or windConnection date moved from 11 Jan 2023 to 1 Nov 2023 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?