AGR SOLAR 2 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bicker Fen 1 Solar | Bicker Fen 400kV Substation | Storage with solar or wind | 57.1 | 31 Oct 2026 Past date +13 mo | Gate 2 | Under Construction/Commissioning |
Recent changes
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Consents Approved
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Status changed from Awaiting Consents to Consents Approved
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Gate marking removed (was Gate 2)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Capacity changed from 50 MW to 50 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 26 Sep 2025 to 31 Oct 2026 (+13 months)+13 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Given a Gate 2 connection offerGate 2
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Capacity changed from 7 MW to 7.1 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Connection date moved from 1 Apr 2035 to 1 Apr 2033 (−24 months)−24 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 May 2025 to 26 Sep 2025 (+4 months)+4 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Technology changed from Solar to Storage, Solar
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 2: Technology changed from Solar to Storage, Solar
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Sep 2025 to 30 May 2025 (−4 months)−4 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windRestructured from 1 stage (50 MW from 31 Oct 2023) to 2 stages (50 MW from 30 Sep 2025, 7 MW from 1 Apr 2035). First connection date +23 months+23 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection point changed from Bicker Fen GSP to Bicker Fen 400kV Substation
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windSubstation name updated in the register (from Bicker Fen to Bicker Fen GSP)
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection date moved from 1 Jul 2023 to 31 Oct 2023 (+4 months)+4 mo
- Bicker Fen 1 SolarEngland and Wales, Storage with solar or windConnection date moved from 7 Jan 2023 to 1 Jul 2023 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?