Berryburn 275/33kV GSP Substation
North Scotland, SSEN Transmission
3projects in the register
160 MWstill to connect
160 MWof that with Gate 2 offers
0 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Berryburn Extension Wind Farm | BB2 WIND FARM LIMITED | Onshore wind | 43.2 | 31 Oct 2027 | Gate 2 | Consented |
| Cairn Duhie Wind Farm | Cairn Duhie Energy Limited | Onshore wind | 67.2 | 31 Oct 2028 | Gate 2 | Consented |
| Corshellach Battery Energy Storage System | Corshellach Energy Storage Limited | Storage | 49.9 | 31 Oct 2028 +12 mo | Gate 2 | Consented |
Recent changes
- Cairn Duhie Wind FarmNorth Scotland, Onshore windStatus changed from Scoping to Consented
- Corshellach Battery Energy Storage SystemNorth Scotland, StorageStatus changed from Scoping to Consented
- Corshellach Battery Energy Storage SystemNorth Scotland, StorageConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)+12 mo
- Corshellach Battery Energy Storage SystemNorth Scotland, StorageGiven a Gate 2 connection offerGate 2
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose