Berryburn Extension Wind Farm
- Connection date
- 31 Oct 2027 +23 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 43.2 MW
- Connected now
- 0 MW
- Still to connect
- 43.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001558
- In the register since
- August 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Aug 2026 registerConnection date moved from 30 Nov 2025 to 31 Oct 2027 (+23 months)
- 7 Aug 2026 registerGiven a Gate 2 connection offer
- 6 Feb 2026 registerConnection point changed from Berry Burn GSP to Berryburn 275/33kV GSP Substation
- 30 May 2025 registerStatus changed from Scoping to Consents Approved
- 31 Jan 2025 registerConnection date moved from 31 Oct 2024 to 30 Nov 2025 (+13 months)
- 29 Aug 2023 registerAdded to the register
Also at Berryburn 275/33kV GSP Substation
Substation view2 other projects, 160 MW still to connect at this substation in total.