Cairn Duhie Wind Farm
Cairn Duhie Energy Limited at Berryburn 275/33kV GSP Substation
- Connection date
- 31 Oct 2028 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 67.2 MW
- Connected now
- 0 MW
- Still to connect
- 67.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001743
- In the register since
- March 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 11 Aug 2026 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 11 Aug 2026 registerGiven a Gate 2 connection offer
- 21 Jul 2026 registerCustomer changed from Renewable Energy Systems Limited to CAIRN DUHIE ENERGY LIMITED
- 6 Feb 2026 registerConnection point changed from Berry Burn GSP to Berryburn 275/33kV GSP Substation
- 9 Dec 2025 registerCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
- 29 Jul 2025 registerCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
- 31 Mar 2023 registerAdded to the register
Also at Berryburn 275/33kV GSP Substation
Substation view2 other projects, 160 MW still to connect at this substation in total. 43.2 MW is due to connect here before this project’s connection date of 31 Oct 2028.